Complete steps of cement plant process
Step 1:Raw materials Preparation--Limestone crushing
a. Process introduction: Limestone is the main raw material in cement production , and most factories are located near the limestone by blasting or use the loader to the mining of raw materials limestone , transported to the crusher into fragments .
b. The main raw material:limestone,clay,iron ore
Step 2:Raw material grinding --Limestone , clay , iron and other raw materials
a. Process introduction: the use of ball mill or vertical mill raw material is ground to a powder, and then by conveyor transport to preblending yard for storage and further material mixed
b. The main raw material: limestone , clay , iron and other raw materials
pec | technical parametere | speed reducer | motor | supporting quantity | |||
(m) | rev | slope | output | type | type | power | |
(r/min) | (%) | (t/h) | (KW) | ||||
Φ1.6x32 | 0.58~2.85 | 4 | 2 | ZQ75-50 | YCT250-4A | 18.5 | 3 |
Φ1.6/1.9x36 | 0.53~1.59 | 4 | 2.5~3 | ZQ110-7 | YCT250-4B | 22 | 3 |
Φ1.9x39 | 0.53~1.59 | 4 | 3~3.4 | ZQ125-7 | YCT315-4A | 37 | 3 |
Φ2.2x45 | 0.214~1.64 | 3.5 | 4~5 | main:ZS125-5 | YCT315-4B | 45 | 3 |
auxiliary:ZQ40-40 | Y112M-4 | 4 | |||||
Φ2.5x50 | 0.62~1.5 | 3.5 | 5~6 | main:ZS165-5 | YCT355-4A | 55 | 3 |
auxiliary:ZS50-1 | Y160M-6 | 7.5 | |||||
Φ2.5x55 | 0.62~1.5 | 3.5 | 5~6 | main:ZS165-5 | YCT355-4A | 55 | 3 |
auxiliary:ZS50-1 | Y160M-6 | 7.5 | |||||
Φ2.8x55 | 0.62~1.5 | 3.5 | 6~7 | main:ZS165-6 | YCT355-4B | 75 | 3 |
auxiliary:ZS50-1 | Y160L-6 | 11 | |||||
Φ3.0x60 | 0.5~1.5 | 3.5 | 7~9 | main:ZS165-3 | ZSN-280-11B | 125 | 4 |
auxiliary:ZS50-1 | Y160L-6 | 11 | |||||
Φ3.2x64 | 0.4~1.5 | 3.5 | 8~10 | main:ZL130-16 | ZSN-280-11B | 190 | 4 |
auxiliary:ZL50-10 | Y180L-4 | 22 | |||||
Φ3.5x70 | 0.4~1.5 | 3.5 | 12~14 | main:ZSY500-40 | ZSN-315-082 | 280 | 4 |
auxiliary:ZL50-14 | Y180L-4 | 22 | |||||
Φ4x80 | 0.4~1.5 | 3.5 | 16~20 | main:ZSY630-35.5 | ZSN-315-12 | 355 | 4 |